CALGARY, ALTA. – A difficult chapter in Calgary’s water history is nearly over, as crews prepare to connect the new Bearspaw South Feedermain Improvements Stage AStatusUnder ConstructionValue$235.4MLocationCalgary, AB T2P 4K7SectorPublic – CityTypeWater/SewerData as of October 26, 2026 into the existing water system, beginning Nov. 4.
According to a release, while this work is underway, city-wide Stage 4 outdoor water restrictions and indoor water conservation will be needed for approximately four weeks to reduce demand while the water supply is limited.
The beleaguered feeder main, which provides treated drinking water to 60 per cent of the city, burst once in 2024, leading to months of water restrictions and then ruptured again in late December 2025, forcing a new round of restrictions in the city of 1.6 million people.Â
As a result, the immediate decision was made to replace the line. The project is adding a parallel steel pipe of the same size as the existing one which will take over service from the current line.Â
Once connected, crews will begin the final commissioning work required to bring the new pipe into service by the end of this year.
“The November connection is a significant phase of the project because it is when the new feeder main will be integrated into Calgary’s existing water system,” said Michael Thompson, Chief Operating Officer – Water, in a statement. “Over the past several months, our focus has been on advancing Âé¶¹´«Ã½Ó³» while securing the specialized materials needed to complete this work. With the majority of those materials now onsite in Calgary and the rest of the materials scheduled to arrive on time, we’re positioned to move into this final phase and deliver on a key investment in Calgary’s water infrastructure that will help reduce the risk of future major disruptions.”
In order to complete the connection of the new pipe, the existing Bearspaw South Feeder Main must be temporarily shut down. During this period, the amount of water that can be distributed across the city will be significantly reduced to 500 million litres a day.
No outdoor water use will be permitted during this time, and all Calgarians are being asked, as well as those in Airdrie, Chestermere, Strathmore and Tsuut’ina Nation, to save water indoors by taking the following actions:
- Run dishwashers and laundry only when full.
- Flush toilets only when needed.
- Take shorter showers. Aim for three minutes.
“We know Calgarians have already done a tremendous job reducing water use when needed,” said Thompson. “The actions people take during this period will help us complete this work safely and successfully while protecting water services across the city.â€�
Once the new feeder main has been connected, crews will focus on preparing the new line for service. This includes disinfecting the pipe, filling it with water and completing the water quality testing required. This process will take approximately two to three weeks.