Yukon Energy fires prime contractor in delayed $35M battery-storage project

The Canadian Press
Yukon Energy fires prime contractor in delayed $35M battery-storage project

WHITEHORSE – Yukon’s electric utility says it has fired its prime contractor in a $35-million battery storage project meant to help the territory deal with peak winter power demands.

Yukon Energy says it is taking over as the prime contractor after dismissing SunGrid Solutions, which did not immediately respond to a request for comment.

The project was set to be complete in 2023, but the Crown corporation says SunGrid failed to achieve “substantial completion” within its contracted time frame.

Yukon Energy says when the project is complete it will be the largest grid-scale battery storage system in the North, and one of the largest of its kind in Âé¶¹´«Ã½Ó³»­.

Construction began in April 2022 at the site in Whitehorse on Kwanlin Dun First Nation Settlement Land, with Ottawa contributing about $16.5 million of the cost and Yukon Energy providing the rest.

The project is now expected to come online in 2027, with Yukon Energy Minister Ted Laking saying the public utility has been directed to conduct an independent review of procurement and lessons learned to address what happened.

“This work is about accountability, transparency and continuous improvement,” Laking says in a statement, adding the results of the review will be publicly released.

“The lessons learned through this review will improve our ability to deliver on the energy projects required for the territory’s future.”

Yukon Energy vice-president of capital projects Paul Murchison says the utility is now focused on getting the battery-storage project “back on track.”

“We have carefully considered the challenges, the work remaining and the options available to us,” Murchison says in a separate statement.

“We believe this change provides the best path toward completing the project safely and responsibly.”

Yukon Energy says it is also pursuing “damages and other remedies” under its terminated contract with SunGrid, although it adds that doesn’t mean the utility will initiate legal proceedings against the company.

©2026 The Canadian Press