VANCOUVER – Thanksgiving weekend meant turkey dinners and family gatherings, but it also meant saying goodbye to one of B.C.’s iconic structures.
From Oct. 9 to 11 the Pattullo Bridge arch was removed and lowered onto a barge for dismantling and recycling.
The process happened over a period of approximately 48 to 60 hours and was visible from locations along the Fraser River such as Brownsville Bar Park in Surrey and Westminster Pier Park or Albert Crescent Park in New Westminster.
According to a fact sheet from the province, strand jacks, which are specialized hydraulic linear winch systems, were used to lower the steel arch onto barges on the Fraser River where it was then transported to the project site for further dismantling and recycling. Detailed deÂé¶¹´«Ã½Ó³» engineering design had been completed for the Pattullo Bridge deÂé¶¹´«Ã½Ó³», followed by third party engineering reviews and concrete components had been removed to lower the weight of the arch.
Crews also installed temporary bracing and beams on the steel arch to support it during lowering and dismantling.
DeÂé¶¹´«Ã½Ó³» is the responsibility of Fraser Crossing Partners, the government’s contractor for the $1.637-billion replacement job, which included building the new stal̕əwÌ“asÉ™m (Riverview) Bridge crossing.
Fraser Crossing Partners is a 50/50 joint venture between Aecon and Acciona with responsibilities to design, build and partially finance the project.
DeÂé¶¹´«Ã½Ó³» work began in February and targeted completion is anticipated for the end of 2027.