Major infrastructure upgrades begin on King Street West in Toronto

DCN-JOC News Services
Major infrastructure upgrades begin on King Street West in Toronto

TORONTO — The City of Toronto and the Toronto Transit Commission (TTC) have started major infrastructure work on sections of King Street West, which will continue through 2027.

This work is part of a multi-year infrastructure renewal program between the city and TTC that began in 2020 to replace aging watermain infrastructure and renew streetcar tracks along the King Street corridor.

The Âé¶¹´«Ã½Ó³»­ schedule is as follows:

– Dufferin Street to Close Avenue: Work underway now until fall 2027.

– Spadina Avenue to Portland Street: As early as December to summer 2027.

– Bathurst Street to Shaw Street: Spring 2027 to late 2027.

– King Street West and York Street intersection: Summer 2027.

– Charlotte Street to University Avenue: Fall to winter 2027.

Construction will be completed in phases to help minimize disruptions while watermain and streetcar infrastructure is renewed, a release notes. Temporary traffic restrictions, lane reductions and intersection closures will be required at various stages of the project.

The city and TTC will continue to provide updates throughout Âé¶¹´«Ã½Ó³»­, including information about traffic impacts, Âé¶¹´«Ã½Ó³»­ milestones and transit service changes.

Up-to-date route information and service changes can be found at .