After some splashing about, demolition of Vancouver aquatic centre to go ahead

Peter Caulfield
After some splashing about, demolition of Vancouver aquatic centre to go ahead
CITY OF VANCOUVER — Pictured is a conceptual artistic rendering of the north approach to the Vancouver Aquatic Centre. The existing centre is slated for demolition.

Following the expiry of an interim injunction in early November 2026,

demolition work on the RFP Construction Manager – Vancouver Aquatic CentreStatusPost-BidValue$140MLocation1050 Beach Ave, Vancouver BCSectorPublic – CityTypeSwimming Pools · RenovationData as of November 17, 2026 (VAC) will go ahead following a delay.

The indoor swimming pool will be demolished and replaced with a new facility on the same site on Beach Avenue in the city’s west end, not far from the north end of the busy Burrard Bridge.

The source of the delay was an objection by the to plans for a new aquatic centre that call for a 25-metre pool to replace the existing 50-metre tank.

POVAC argued a 25-metre pool ran contrary to the results of a 2022 Vancouver plebiscite that approved borrowing $103 million for a 50-metre replacement pool.

In addition, local swimming groups say a 50-metre pool at the aquatic centre was critical to numerous communities and a smaller pool would cause many of these swimming groups to scatter around Greater Vancouver.

 

Shown is a rendering of the leisure pool with a viewing area in the far distance.
CITY OF VANCOUVER — Shown is a rendering of the leisure pool with a viewing area in the far distance.

 

The Vancouver Board of Parks and Recreation argued a 50-metre pool was impossible within the current aquatic centre’s building footprint.

In October of this year, POVAC asked for and received an injunction to stop demolition of the VAC, but the injunction’s expiration means the society’s luck has apparently run out.

Nevertheless, the decision is being appealed at the BC Court of Appeal.

If it proceeds, the demolition and renovation work on the aquatic centre is scheduled to finish in late 2029.

The VAC was permanently closed in June. Its absence for three years will be widely felt. In 2025, it recorded 329,816 visits, not including attendance for swimming lessons.

Whatever replaces it, the VAC has come to the end of the road.

According to the parks board and the City of Vancouver, the aquatic centre, which opened in 1974, has structural problems that have accelerated the need for its replacement.

“Studies have determined that renovation is not a viable long-term option, and the building will be removed and replaced on the existing site,” they say.

Planning for the VAC’s renewal considered “a range of aquatic programming needs…Based on this analysis, it was determined that a 50-metre pool could not be accommodated within the project parameters.”

When the new aquatic centre has been completed three years from now, it will “support a wide range of aquatic and recreation needs.”

Some of the features are:

  • Aquatic spaces that support lap swimming, diving, lessons, leisure swimming, rehabilitation and fitness programs;
  • a dedicated diving tank with multiple board heights for training and competition;
  • a flexible pool design, including a movable floor to accommodate a range of programs and users;
  • a larger hot pool and sauna, allowing for increased adaptive and lesson programming; and
  • a larger fitness room with more space and equipment and multi-purpose room for community programs and events.

The VAC is not the only Vancouver municipal swimming pool that is in need of renewal.

The popular Kits Pool), the city’s largest outdoor swimming pool, is also showing its age.

Built in 1931, rebuilt in 1978 and located right next to English Bay, the pool is built on a floodplain and wave hazard zone.

As a result, Kits Pool is vulnerable to projected sea-level rises and increasing storm surge threats that are expected to worsen over time.

The city and the parks board say Kits Pool has reached the end of its life and “faces challenges related to aging infrastructure, structural deterioration and increasing impacts from storms and climate change.”

In 2023 the pool was leaking 30,000 litres of water an hour due to cracks and breaks in re-circulation pipes

Vancouver City Council has asked staff to include the rehabilitation of Kits Pool in the city’s 2027–2030 capital plan and to report back as part of the mid-term capital plan update.

Meanwhile, in another part of the city’s west side, the Kerrisdale Pool

closed for upgrades in June 2025 and was originally scheduled to reopen in January 2026.

Opened as an outdoor pool in 1956, the Kerrisdale Pool was converted into an indoor facility with a fabric dome roof in 1995.

After refilling the pool in preparation for reopening, however, a leak was found in one of its principal drains, causing a delay while repairs were completed.

Following repairs and assessments, the pool reopened in September 2026.