New $117M extension, bridge connecting Oakville and Burlington near completion

Dena Fehir
New $117M extension, bridge connecting Oakville and Burlington near completion
HALTON REGION — The $117 million Wyecroft Road extension and bridge project in Oakville, Ont. are both on time and on budget. Halton Region awarded the project’s engineering to WSP Âé¶ą´«Ă˝Ół»­ and the building contract to Dufferin Construction.

The $117 million Construction of Wyecroft Road (Reg.Rd 45) from Burloak Drive (Reg. Rd 21) to Bronte Road (Reg. Rd 25), in the Town of OakvilleStatusAwardValue$117.5MLocationWyecroft Rd, Oakville ONSectorPublic – CountyTypeRoads / HighwaysData as of November 3, 2026 project in Oakville, Ont. are both on time and on budget.

Although weather dependent, the new bridge and road extension are anticipated to open by Nov. 30.

“The Âé¶ą´«Ă˝Ół»­ of the new bridge and road extension began in October 2023 and has included the installation of new multi-use paths and a watermain. The project is now approximately 97 per cent complete,” said Lee Anne Jones, Halton Region commissioner of public works.

 

HALTON REGION

 

The road extension and bridge crossing will connect the City of Burlington and Town of Oakville over Bronte Creek by extending Wyecroft Road from Burloak Drive in the west to Bronte Road in the east.

Halton Region awarded the project’s engineering to WSP Âé¶ą´«Ă˝Ół»­ and the building contract to Dufferin Construction.

According to the Halton Region website, benefits of the project include:

  • Providing motorists with another route, relieving traffic congestion on both local roads and the Queen Elizabeth Way.
  • Reducing the amount of time it takes to commute to Appleby and Bronte GO stations.
  • Connecting adjacent employment lands, providing business owners, employees and consumers easier access to work and retail.
  • Providing alternative transportation options with new pedestrian and cycling infrastructure.
  • A new watermain to service future growth and support the water supply in Oakville.

Project improvement components include:

  • A new four-lane roadway
  • Bridge
  • Maintaining clean drinking water
  • Multi-use pathways
  • New on-road bike lanes

The project dates back to 1994 with the Town of Oakville’s environmental assessment study. Regional funding was approved and design began in 2019 with Âé¶ą´«Ă˝Ół»­ kicking off in the fall of 2023.

Halton Region received $53.11 million in funding from the Province of Ontario for the project.

Outstanding tasks include:

  • Removal of temporary traffic signals and installation of permanent traffic signals at Bronte Road and Wyecroft Road.
  • Final paving of the westbound bridge and Bronte Road and Wyecroft Road intersection.
  • Pavement markings, railings and other minor finishing.

Once operational, the extension and bridge are designed to handle over 4,000 trips per day, about 2,000 vehicles during the afternoon peak, helping to ease congestion on the QEW, Rebecca Street and Lakeshore Road.