‘A sad tale’: Recommendations issued in troubled Winnipeg police HQ inquiry

Jean Sorensen
‘A sad tale’: Recommendations issued in troubled Winnipeg police HQ inquiry
DEBRA MCEVOY — Recommendations stemming from the inquiry into the troubled Winnipeg police headquarters renovations have been issued with many providing best practices and advice contributed by a Winnipeg Construction Association panel.

Recommendations stemming from the inquiry into the troubled Winnipeg police headquarters renovations where costs soared to $214 million – almost double the budget – have been issued with many providing best practices and advice contributed by a Winnipeg Construction Association (WCA) panel.

The inquiry’s 20-month final report is also a detailed and troubling account of falsified financial documents, inflated billing claims, inappropriate financial dealings and serious conflicts of interest.

The inquiry found police headquarters contractor Caspian Construction has overcharged the city more than $40 million. A lawyer announced at the final day’s hearing Caspian had paid the $28 million it promised as part of a 2023 legal city settlement.

The WCA issued a statement that it “unequivocally condemns� the misconduct identified by inquiry commissioner Garth Smorang.

“There is no place for the conduct described in the report in our industry,â€� Darryl Harrison, WCA president, said. “Our industry is overwhelmingly made up of honest, hardworking Âé¶¹´«Ã½Ó³»­ professionals who take pride in their work and integrity.â€�

Smorang recommended the Manitoba Prosecutions Service (MPS) be more open in providing information to the media and the public in investigations and decisions not to prosecute.

In December 2014, the RCMP executed a search warrant on police headquarters contractor Caspian Construction and seized 46 boxes of documents and computers to carry out a five-year investigation.

In 2019, MPS issued a statement that there was insufficient evidence to approve criminal charges and the city requested the province call an inquiry into the dealings.

Smorang said his jurisdiction in the inquiry was focused on providing measures that would instil public confidence in the city’s ability to handle large capital expenditure projects and prevent mismanagement.

A total of 25 recommendations are set out in Smorang’s 193-page report entitled, A. Smorang’s recommendations are focused on more oversight, having city staff declare they have no conflict of interest and transparency in financial documents.

The issue stems from the 2009 city purchase of a former Âé¶¹´«Ã½Ó³»­ Post building as a replacement for the Winnipeg Police Headquarters, which was then located on Princess Street. The Âé¶¹´«Ã½Ó³»­ Post building required extensive renovations.

The soaring project cost and the ensuing audit resulted in two civil proceedings that were brought in relation to the project, one regarding Âé¶¹´«Ã½Ó³»­ deficiencies (2018) and the other related to civil fraud (2020).

Smorang’s recommendations impact both city officials and contractors. Those relating to the Âé¶¹´«Ã½Ó³»­ are listed below.

Recommendation number one advocates lawyers should draft the Request for Proposals documents, retendering should occur for major addendums and the RFP should be used as a screening method to ensure contractor competency.

“I also recommend that if a JV (joint-venture) partner withdraws, that a best practices and business analysis is undertaken to determine the next step,� the report also advised.

“We heard from the WCA panel that they were puzzled, years after the fact, by how a legal entity that did not bid for the project (Caspian alone) ended up with the Âé¶¹´«Ã½Ó³»­ contract.â€�

Recommendation number four called for proper resource allocations of large projects as the inquiry found the lack of resources impacted both companies and staff brought into the project. The WCA had advocated for proper resourcing and stressed the need for more real time communications for cost impact, schedule changes, quality issues and evolving risk.

“What we learned during the inquiry was that the original budget of $125 million, that included $105 million for redevelopment, was not established with any rigor and was increased by $50 million for redevelopment just five months after it was approved. A change of $50 million before the project is up and running shows the first budget was never realistic,� Smorang said in his report.

Recommendation number five calls for the city to liaison with industry to determine how upcoming projects might be impacted by others occurring and the demand on resources.

The WCA panel advised market sounding could help assess capacity, identify procurement risks, understand contractor concerns and gain advice on different delivery models.

The panel also advised that early consultation provided the industry with knowledge of upcoming projects and market needs such as recruitment and retention of workers.

Smorang said a concern was discussing projects that were yet approved with industry, but confidentiality agreements could be used.

“While there might be some risk of premature disclosure of a potential project, I am of the opinion that keeping the industry informed outweighs these risks,� he wrote.

Recommendation number eight urged all large projects should engage a quantity surveyor to manage the payment process and the surveyor should have copies of the subtrade contracts and subtrade should submit invoices that detail what work has been done on the project.

The commissioner said in his report the WCA panel made it clear their member companies were always willing to provide copies of necessary documents and “fully supported an open book and transparent system.�

Smorang said it is clear to him if such a vigilant system had been in place “the altered invoices submitted by Caspian would have been quickly revealed as inauthentic.�

Recommendation number 11 wants the Manitoba government to look at BIM and consider mandating it for all municipalities’ large-scale projects and that the city give preference to those RFP contractors using the technology.

The WCA acknowledged the growing role of BIM on large-scale projects and urged greater adoption.

Recommendations 15, 16 and 17 address conflict of interest and requires elected officials on hiring or selection committees to disclose any relationship to applicants or companies as well as city staff to disclose any relationship.

The complete recommendations and the inquiry’s detailed analysis of how the project went sideways can be found in the commission report at: .