HALIFAX – Nova Scotia’s Progressive Conservative government is spending more than $31,500 a month on a Cape Breton health project that’s on hold and considered unaffordable.
Those details are included in documents obtained by the Nova Scotia NDP through a freedom of information request. The records contain a summary note to the health minister saying the costs of building a new hospital and long-term care facility in the community of New Waterford have doubled since the Liberal government began planning the proposed complex in 2018.
Official Opposition NDP Leader Claudia Chender called the situation a “travesty,” as residents in the former coal-mining town have been waiting years for vital health care infrastructure upgrades.
“Now we’re literally paying for nothing when that money could go toward some much needed health resources in New Waterford, for a community that has waited for far too long,” Chender told reporters Thursday.
The documents say the company contracted to build the new infrastructure is receiving a $31,555 monthly management fee to maintain the site, which is a temporary reduction to a previously negotiated $326,000 monthly fee.
The reduction reflects the “substantially reduced” activity on the site.
Health Minister Michelle Thompson said Thursday she has no update on the New Waterford health centre’s progress and she wants to speak to community members before moving forward.
“Here we are eight years later, I believe there’s been a lot of change in health care since then. So is that the right project for now? For today? We have to talk to the community about that,” the minister said after a cabinet meeting.
Thompson said the government hasn’t set up a meeting with the community yet, but she added it will happen before the end of the year.
“I know it’s unsettling, but it’s due diligence,” Thompson said.Â
The minister confirmed the province is continuing to pay the $31,555 monthly fee to PCL Construction to keep them on the project. A spokesperson with Build Nova Scotia says that covers trailers, lighting, fencing, a storage container and a power panel that remain on site.Â
“That is money we have to pay to keep those assets there, and so as we continue to move forward and re-scope … we don’t want to dismantle that site in the interim,” Thompson said.
If the project’s contract is cancelled, the province would have to pay PCL Construction approximately $652,000, according to a briefing note included in the documents obtained by the NDP.
The documents also include an email sent in May by a group of New Waterford physicians who shared major concerns about the lack of progress on the new health-care centre. The physicians said the delays have “eroded confidence” in the project’s future.Â
The email sent to Thompson, Premier Tim Houston and the former interim CEO of the health authority says the continued lack of communication from the provincial government is “deeply disappointing and increasingly concerning.”
It says doctors, health-care staff and residents have invested years of advocacy and planning in the New Waterford health hub, and the building of this new centre has been “central to our physician recruitment efforts and long-term planning” for health care in the region.
“Meanwhile, we continue to provide care in a facility that is no longer adequate for modern health-care delivery,” it continues.
The email says the community’s existing hospital, which opened in 1963, has poor ventilation, insufficient space and poor accessibility, which pose challenges for health-care providers and patients.
Liberal Leader Becky Druhan said Thursday the Progressive Conservative government has “refused to follow procurement rules, refused to make health-care purchases responsibly, and that has put them in a very difficult position.”
A March report from Nova Scotia’s auditor general found that Nova Scotia Health has been inappropriately using alternative procurement and not following provincial policy.
Druhan, who left the PCs in October 2025, said as a result, the province is paying too much for health-care projects that are underway.Â
“And now they’re having to make really terrible choices to not move ahead with other projects that were promised … it’s mismanagement,” she said.