Industry Perspectives Op-Ed: What one Alberta commercial project taught me about pricing geotechnical risk early

Joseph Areghan
Industry Perspectives Op-Ed: What one Alberta commercial project taught me about pricing geotechnical risk early

On one Alberta commercial project, the development looked straightforward at first.

The site had room for the building, parking and servicing. From the surface, there was little to suggest the ground would become an important cost driver.

Then we drilled.

The investigation encountered variable fill, high-plasticity clay, localized sand seams and a relatively high groundwater table. Seepage developed where the sandier zones intersected the boreholes.

None of these conditions are unusual in Alberta. What mattered was how quickly they began influencing foundations, earthworks, groundwater management and Âé¶¹´«Ã½Ó³»­ cost.

 

It was never just about bearing capacity

One of the first questions I am usually asked is, “What allowable bearing pressure can we use?�

It is reasonable, but after many years in practice, I rarely consider it the first question that needs answering.

On this site, the bigger issue was whether shallow foundations could be constructed consistently on suitable material.

High-plasticity clay was present beneath portions of the site. Moisture variation, disturbance and long-term volume change also mattered.

A footing founded on competent clay during dry conditions may behave differently if the founding surface is exposed to water before concrete placement.

A bearing-pressure number without Âé¶¹´«Ã½Ó³»­ context can therefore be misleading. The foundation needs to work not only in the calculation, but in the excavation.

 

The sand seams changed the groundwater discussion

The site was predominantly cohesive, but localized sand seams created pathways for seepage.

A contractor can excavate through stiff clay and suddenly encounter water entering through a thin sand seam. Conditions can change quickly.

Water at foundation level can soften exposed clay, complicate inspection and interfere with concrete placement.

For shallow foundations, the response may involve localized pumping, sumps, granular working surfaces or sequencing excavation so founding surfaces are not left exposed longer than necessary.

The mistake is assuming that because the surface looks dry, groundwater will not affect Âé¶¹´«Ã½Ó³»­.

 

Deep foundations brought another issue: Casing

As foundation options were reviewed, pile Âé¶¹´«Ã½Ó³»­ also had to account for groundwater and granular seams.

Where bored piles extend through cohesive soils containing wet sand or water-bearing layers, the borehole may not remain open simply because the surrounding clay appears competent.

Sand seams can run, slough or introduce water into the excavation. Temporary casing may therefore be required to maintain the pile excavation and allow reinforcement and concrete placement.

Casing adds equipment, handling and time, and can reduce pile-production rates. That matters before Âé¶¹´«Ã½Ó³»­ prices are fixed.

If the condition is identified before tender, contractors can price it. If it appears after the piling rig arrives, it becomes a conversation about extras.

 

High-plasticity clay creates its own decisions

High-plasticity clay is common across Alberta and can be underestimated.

It may provide adequate bearing capacity and still require careful management because of moisture sensitivity, shrink-swell behaviour, difficult compaction when wet, frost effects and deterioration under Âé¶¹´«Ã½Ó³»­ traffic.

One of the most important field lessons is to protect exposed clay.

Once a prepared subgrade becomes wet and remoulded, the solution is often excavation and replacement of material that was acceptable days earlier.

I have seen more money spent correcting damaged subgrades than protecting them properly.

 

Earthworks were where soil became dollars

Variable fill and unsuitable near-surface soils created another commercial decision.

It is easy for an engineer to write, “Remove unsuitable material and replace with engineered fill.�

But every cubic metre removed carries excavation, trucking, disposal or stockpiling, replacement material, compaction and testing.

The more useful question is: What can safely stay, what must be removed and where can excavated material be reused?

High-plasticity clay unsuitable beneath a building may still be useful in landscaped or non-structural areas.

A good earthworks strategy can save far more money than wholesale removal.

 

The project reinforced a simple lesson

Nothing we encountered was exotic. It was a combination familiar to Alberta Âé¶¹´«Ã½Ó³»­: high-plasticity clay, variable fill, groundwater, sand seams and seepage.

The value of geotechnical engineering on a commercial project is not simply providing bearing pressures or pile capacities. It is helping the team understand what the ground is likely to do when Âé¶¹´«Ã½Ó³»­ starts.

Will water enter the excavation? Will clay soften if exposed? Can excavated material be reused? Will bored piles require casing? Are shallow foundations still economical? Does the contractor need dewatering or additional granular material?

Those questions affect the estimate just as surely as concrete or reinforcing steel.

After enough years working with soil, one lesson becomes difficult to ignore: Ground conditions rarely become cheaper once Âé¶¹´«Ã½Ó³»­ begins.

Investigating them early does not eliminate geotechnical risk. It gives the team the opportunity to manage and price that risk before the excavator makes the decision for them.

Joseph Areghan, P.Eng., is with , an Alberta engineering consultancy providing geotechnical engineering, environmental consulting and Âé¶¹´«Ã½Ó³»­ materials testing services. Send Industry Perspectives Op-Ed comments and column ideas to editor@dailycommercialnews.com.