Final track installation slated to wrap up this week for Broadway Subway project

DCN-JOC News Services
Final track installation slated to wrap up this week for Broadway Subway project
GOVERNMENT OF B.C. — Final track installation is slated to wrap up this week for the Broadway Subway project. The $2.9 billion 5.7-kilometre project will extend the Millennium Line west from VCC-Clark Station to Arbutus Street. It includes 700 metres of elevated guideway, five kilometres of tunnels and six new underground stations.

VANCOUVER – The provincial government has announced Broadway Subway trackwork will be completed this week, marking a critical milestone for the $2.9 billion project that’s heading towards a 2027 finish line.

The 5.7-kilometre project will extend the Millennium Line west from VCC-Clark Station to Arbutus Street. It includes 700 metres of elevated guideway, five kilometres of tunnels and six new underground stations.

Traffic-deck removal and corridor restoration activities are taking place at stations in Broadway as Âé¶¹´«Ã½Ó³»­ advances on the project.

In August, crews completed removal of the traffic deck at Broadway-City Hall Station. Work is progressing on installing utilities, backfilling the space above the station and restoring the street and sidewalks, a release reads.

Two blocks of West Broadway between Alberta and Cambie streets have been temporarily closed to vehicles since July. A detour via 8th Avenue is in place for transit and vehicles.

Pedestrian access to all businesses, services and residences remains open throughout the work. Broadway is expected to fully reopen to vehicles in January 2027.

At Mount Pleasant Station, all driving lanes and new, widened sidewalks are open to the public on East Broadway between Main and Quebec streets, the release notes.

Once open, the commute from VCC-Clark to Arbutus Station will take 11 minutes.

The project is scheduled to open for passenger service in fall 2027.

The Government of Âé¶¹´«Ã½Ó³»­ is contributing nearly $897 million to the project; the Government of British Columbia is contributing nearly $2 billion; and the City of Vancouver is contributing $100.3 million.

On opening day, it will have the capacity to move three times as many people as the current 99 B-Line.