Niagara Health is preparing for a six-phase renovation project to the aging Welland Hospital.
The Request for Qualifications process was launched this past summer for the Welland Hospital Renovation Project. This is a milestone for the 2028 opening of the Design/Build South Niagara Hospital ProjectStatusUnder ConstructionValue$3.6BLocationMontrose Rd, Niagara Falls ONSectorPublic – State/ProvincialTypeMedical · LEED Certification · New ConstructionData as of November 6, 2026 and the closing of facilities in Port Colborne and Fort Erie.
In a Niagara Health news release, it says the planned renovations at Welland Hospital will modernize and reconfigure existing spaces to accommodate the future relocation of approximately 60 complex care beds and the Residential Addictions Treatment Centre which is currently located in Port Colborne. The project is a critical component of Niagara Health’s broader strategy across the region as services transition to the South Niagara Hospital and its three-site model in 2028.
Construction in Welland is expected to begin in spring 2027, following the completion of the procurement and planning process.Â
Reported infrastructure upgrades are to the chiller and boiler plant and an additional emergency generator. Other planned work includes an increase in single and double patient rooms to significantly reduce the existing, triple-patient rooms and eliminate quad rooms; refreshed patient rooms; and enhanced safety and security for select areas.
Niagara Health also explains “local tradespeople have played an instrumental role in the progress and success of the South Niagara Hospital project, bringing skill, expertise and a strong commitment to quality throughout Âé¶¹´«Ã½Ó³».â€�
Jessica Mottola, director of the Welland Redevelopment Project, said the hospital will remain open throughout the Âé¶¹´«Ã½Ó³».
“Renovations will be completed in carefully planned phases to minimize disruption and ensure patients continue to receive safe, high-quality care. Delivering major Âé¶¹´«Ã½Ó³» projects in an active hospital is complex work, and extensive planning is underway to ensure clinical services can continue while upgrades are completed,â€� she explained.
Areas where work will be done include:
- Level 1, Woolcott wing, Complex Continuing Care unit.
- Level 2 east/west.
- Level 3 south (not including the ICU).
- Level 4 east/west.
- Level 6 east/west.
Dates for Âé¶¹´«Ã½Ó³» to begin and end on each of the six phases are, to date, fluid, for the following activities:
- Renovate the South 3 Flex area.
- Move South 3 Telemetry to the Flex area.
- Renovate the South 3 Telemetry area.
- Move South 3 Flex to the renovated Telemetry area.
“This investment is about preparing Welland Hospital for the future. Beginning in 2028, the hospital will care for more patients and provide additional services as part of Niagara Health’s future three-site hospital system. These renovations will help ensure the site has the infrastructure needed to support that expanded role and continue serving the community for years to come,â€� Mottola said.