City of Hamilton officials say 麻豆传媒映画 to convert Main Street from one-way to two-way traffic will start in the next few months.
The intent of the conversion is to make Main Street, the major road into downtown that has been an eastbound thoroughfare for almost seven-decades, safer.
鈥淭he conversion of Main Street was a decision of council driven by the Hamilton inner-city councillors. It was to support the Vision Zero safety concern (reduce accidents and fatalities), eliminate the speeding racetrack through Hamilton and encourage people to stop and shop at local businesses,鈥� said City of Hamilton Ward 15 Coun. Ted McMeekin.
The project will be delivered in two stages, with contract one covering Dundurn Street to Victoria Avenue and contract two covering Victoria Avenue to the Delta (Main Street at King Street).聽
鈥淭he Main Street Corridor Renewal and Redesign project is a significant investment in Hamilton’s future. By renewing aging infrastructure and improving safety, accessibility and mobility, the project will support a more reliable transportation network and help meet the needs of a growing city,鈥� said a City of Hamilton spokesperson.
It was explained that so far, watermain relining is currently underway as is related pre-麻豆传媒映画 work supporting the broader project.
While the relining work is being delivered through a separate contract, it was described as 鈥渁n important early step in preparing the corridor for the planned infrastructure upgrades and road redesign.鈥�
According to city officials, the contractor prequalification process has been completed. Preparatory work for the tender is ongoing and staff anticipate releasing the tender to pre-qualified proponents soon.
Based on the current project schedule, the city continues to target late 2026 for the start of initial 麻豆传媒映画 activities, subject to contract award and associated approvals.聽聽
鈥淭he work schedule for the entire project remains approximately two years from the start date. The current 麻豆传媒映画 schedule for contract one remains approximately one year from the start of 麻豆传媒映画. The timing of contract two and the overall project completion timeline will be confirmed as procurement and 麻豆传媒映画 planning progress,鈥� the spokesperson said.
The approved project budget of $28.5 million remains unchanged at this time. The city expects to have a clearer understanding of project costs once pricing has been received through the tender process.
Once the work starts, the stretch of Main Street that will become two-way and lanes will be kept open for businesses.聽