It’s hard to fathom that a $75-billion capital expansion program is being delivered under the radar but that seems to be the case with the Metrolinx GO regional expansion program, covering 600 kilometres of GO rail service.
As outlined by Metrolinx’s head sponsor for GO Expansion Jake Schabas at the recent the transit agency is in the midst of an expansion to increase GO rail capacity and frequency across the region, adding six new GO stations, 71.2 kilometres of new light rail transit, 15.8 kilometres of extended subway in Toronto and 15.6 kilometres of new subway.
Schabas said his presentation would focus on GO regional expansion, leaving out inner Toronto projects such as LRT and the GO Expansion – Union Station Enhancement ProjectStatusUnder ConstructionLocation65 Front St W, Toronto ONSectorPublic – State/ProvincialTypeTransportation Terminals · RenovationData as of October 19, 2026. He explained regional expansion aims to deliver more frequent, two-way, all-day service across much of the GO network, with electrification and faster trains on key corridors, phased in over the next decade.

What started as an Oakville to Pickering commuter service 59 years ago now includes seven lines, including Kitchener, Barrie, Richmond Hill, Stouffville and Milton – “It’s a huge success story from a regional transit perspective,â€� said Schabas.
“The complexity of the program means that it’s somewhat less in everyone’s mind as one of Metrolinx’s big projects,â€� he said during a morning session at the presented recently in Toronto by Transport Futures.
“People are much more familiar with the Ontario Line. They see the hoarding downtown. You know here in Ontario the Hazel McCallion Line Downtown Mississauga ExtensionStatusConceptualValue$50MLocationMississauga, ON L5B 3C9SectorPublic – CityTypeTransportation TerminalsData as of October 19, 2026 is being built. It’s right in the middle of the main street that everyone’s using.
“Whereas on GO, we’re running a service today, so most of our work is actually happening when everyone’s asleep…But it’s much more challenging for us to get the message across as to how much work is actually underway.â€�
Schabas’s presentation highlighted what Metrolinx calls five “missions� – for Lakeshore East; Lakeshore West; Kitchener and Union Pearson Express; Stouffville; and Barrie.
“It’s also spread out over 600 kilometres, so we’ve got works demolishing bridges in Oshawa to build a widened corridor, for example,â€� he said. “So that’s happening, 60 kilometres from downtown. At the same time, we’re doing works out in Georgetown, or we’re doing works out in in Burlington.
“So piecing together what is actually under Âé¶¹´«Ã½Ó³» is a pretty complicated task.â€�
There are no precedents for the type of holistic regional service and expansion GO is undertaking anywhere in North America, Schabas said.
Examples in Munich, Paris
Instead, observers look overseas to the S-Bahn Munchen in Munich, the Reseau Express Regional in Paris and the London Overground in London.
“These are services that are fast, that are frequent, that are all day, that are providing connections into local transit as well as these big hubs that connect to the intercity services,� said Schabas.
Schabas explained GO Expansion’s promised 15-minute service, electrification and new trains depend on a sequence of infrastructure upgrades. Many corridors, including Barrie, Kitchener and Stouffville, still have long sections of single track, limiting the ability to run two-way service.
Metrolinx has spent the past 10 to 15 years widening corridors and building additional platforms and bridges to enable second, third or fourth tracks, said Schabas. The next step is modernizing the signalling system, much of which relies on technology developed decades ago, to safely manage train movements and speeds. The new system will integrate the European Train Control System Level 2.
Safety a priority
After that comes level crossings, where safety is an “absolute priority,� he said.
“Once that is done, that is when we bring in the electrification and the new fleet.�
Among major constructors undertaking the work is ONxpress Transportation Partners, a consortium led by Aecon Concessions, Alstom, FCC Construccion and Deutsche Bahn, awarded the On-Corridor Works project in 2022.
The Transport Futures session was titled Where the Wheels Hit the Road, Rail and Tarmac and besides Schabas it included representatives of the Ontario Ministry of Transportation, VIA Rail Âé¶¹´«Ã½Ó³», the Ontario Motor Coach Association and Air Âé¶¹´«Ã½Ó³».
“I think we made very clear that all the modes have to work together,� said Transport Futures founder Martin Collier, referring to the conference theme.
“It has to be integrated. Like the way that the trains work with the buses, and the buses work with the planes, and you know the role that cars obviously are still going to play.�
A look at the GO expansion’s five ‘missions’
Schabas outlined the missions in more detail during the session. Here is what is included:
- Lakeshore West Mission
Under Construction: Grade separation, Burloak Drive; station accessibility upgrades, Long Branch station; Union Station Rail Corridor (USRC) Phase I, Union Station Enhancement Project (USEP)
In Design: Electrification, USRC to Burlington; upgraded signalling with European Train Control System Level 2 (ETCS L2); new layover, Walkers Line; new layover, Wilson Yard; station accessibility upgrades, Mimico station
- Lakeshore East Mission
Under Construction: New track and civils, Bowmanville Extension; third track reinstatement, USRC to Scarborough Junction
In Design: Electrification, USRC to Oshawa; additional layover tracks, Whitby Rail Maintenance Facility; upgraded signalling; grade separations, Morningside Avenue, Galloway Road and Poplar Road; fourth track, platform and civils, USRC to Scarborough Junction
- Kitchener and UPE Mission
Under Construction: Fourth track, Lansdowne to Dupont
In Design: Electrification, USRC to Pearson; Legacy Union and USRC; upgraded signalling; fourth track, Bloor to Nickle; fourth track and civils, Humberview to Wice; one additional track, Strachan to Bloor; dedicated tracks and civils, Bramalea to Silver; grade separation, Silver Junction; second tracks, Guelph and Acton stations
- Stouffville Mission
Under Construction: Grade separation, Finch Avenue; second track and platform, Mount Joy station; second track, Highland to Underwood; turnback signal, Stouffville station
In Design: Electrification, Scarborough Junction to Old Elm; USRC Phase II, Legacy Union and USRC; upgraded signalling; second track and platform, Kennedy station; special trackwork, Hagerman crossover; fourth track, platform, civils and bridge, USRC to Scarborough Junction and Birchmount Road; station upgrades, Markham station
- Barrie Mission
Under Construction: Second platform, King City station; second track and platform, Concord to Teston, Maple station; second track and platforms, Aurora and Downsview Park stations
In Design: Electrification, USRC to Allandale; upgraded signalling; second track and platform, Caledonia station; second track, Innisfil station; second track and platform, Bradford station; two additional tracks, Strachan to Rogers; second track, Kirby to King Lumber.