A glance at supplier assessments and performance evaluation

Stephen Bauld
A glance at supplier assessments and performance evaluation

An assessment should consider the scope and nature of products purchased from a supplier, the requirements to which the supplier was subject, the circumstances in which the supply was made and any other relevant or extenuating circumstances.

A balanced approach to assessment should be coupled with an appropriate contractual regime of warranties, bonuses and penalties. While the preparation of performance reports should not degenerate into a complaint driven system, instances of dissatisfaction should be catalogued and classified to generate specific areas of concern.

These can then be related to the customer’s requirements as set out in the specifications for the supply contract.

Relevant areas of concern include:

  • Processing of order;
  • timeline of delivery;
  • completeness of delivery;
  • time required to make good backorders;
  • condition of goods on receipt;
  • identified problems with shipments received;
  • time required to correct those problems;
  • comparison of individual supplier results with those of other suppliers furnishing similar goods or services; and
  • identification of potential areas of improvement for the supplier.

Based upon such assessment, it is possible to generate a detailed report of audit findings covering management, facilities and adequacy of the supplier’s quality management system.

Where practicable use may be made of photographs taken during audit. In addition to the detailed report, a management summary, including a recommendation on the supplier’s suitability, should be provided.

It is worthwhile to contrast the fairly basic scheme of performance assessment discussed in the previous paragraph with the wide-ranging contract appraisal support system employed by the United States Department of Defence in relation to its Âé¶¹´«Ã½Ó³»­ contractors.

The following performance areas are considered.

 

Quality control:

  • Quality of workmanship;
  • adequacy of contractor QC plan;
  • implementation of QC documentation;
  • quality of QC documentation;
  • storage of materials;
  • adequacy of submittals;
  • adequacy of QC testing; and
  • adequacy of as-builds.

 

Compliance with safety standards:

  • Adequacy of safety plan;
  • implementation of safety plan; and
  • correction of noted deficiencies.

 

Timely performance:

  • Adequacy of initial progress schedule;
  • adherence to approved schedule;
  • resolution of delays;
  • submission of required documentation;
  • completion of punch-list;
  • submission of updated and revised progress schedules; and
  • warranty response.

 

Effectiveness of management

  • Co-operation and responsiveness;
  • management of resources/personnel;
  • co-ordination and control of subcontractors;
  • adequacy of site clean-up;
  • effectiveness of jobsite supervision;
  • compliance with laws and regulations;
  • professional conduct;
  • review/resolution of subcontractor issues; and
  • implementation of subcontracting plan.

 

Compliance with labour standards

  • Correction of noted deficiencies;
  • payrolls properly completed and submitted; and
  • compliance with labour laws and regulations.

 

Possible ratings might include Outstanding, Above Average, Satisfactory, Marginal, Unsatisfactory in each area plus an overall rating for the entire project.

The ratings given feed into the prequalification process for future work.

Individual supplier performance is, of course, a critical consideration because it relates to the satisfaction of the needs of an individual ordering department within the municipal organization.

However, to enhance municipal operations on a consistent basis, it is generally necessary to approach supplier performance monitoring on a comparative basis. As noted above, strategic planning is optimized when one moves from a known point of origin towards a predetermined destination.

Thus, it is important to compare current results with historic performance. In terms of public service delivery, the overall goals of performance assessment are to help ensure cost effective programs and source delivery and obtaining fair value for money.

To that end, in assessing the overall performance of a municipality’s suppliers, the purchasing department might keep track of several comparative performances with respect to all suppliers across the municipality and with respect to classes of suppliers of a given kind.